PepsiCo
1,128 m2; 0.75 MWth
Feira de Santana, Brazil
25 to 90ᣞC
Beverage
1,212 MWhth/y (1,075 kWhth/y/m2)
Process heat
138,565 m3/y of natural gas
Engineering and solar plant supply (construction contracted to a local qualified EPC)
276 ton/y of CO2



Challenge
A giant multinational in the food & beverage industry, PepsiCo, committed to reduce Scope 1 GHG emissions in its factories as part of its corporate ESG goals. Solar thermal is required to deliver process hot water for the mixing of chocolate and milk for the Toddynho
Solution
TVP integrates the client process hot water circuit with a water-to-water heat exchanger. The mixing process of chocolate and milk uses the renewable heat delivered by TVP which operates as primary heat source. The existing natural gas driven burners are now just a complement to the solar thermal system.